Construction progress update in April 2022 – Road project from Xuan Hung commune connecting with road from Tho Xuan town to Lam Son – Sao Vang urban area, Tho Xuan district

At the end of April 2022, INVESTCORP Land Thanh Hoa Company Limited has gathered machinery, materials and human resources to implement the construction of the road project from Xuan Hung commune connecting with road from Tho Xuan town to Lam Son – Sao Vang urban area, Tho Xuan district. The works implemented in the month including digging, dredging organic soil, digging foundation - mold – bench cut reached 65% of the workload; construction of embankment of road K95 achieved 55%, K98 achieved 7% of the contract value.

In May 2022, INVESTCORP Land Thanh Hoa will focus on completing the works related to the road foundation, striving to clear the road foundation, inspect K95, proceed to the construction of the K98 foundation layer according to the construction progress in the contract.