Construction progress update in August 2022 – Road project from Xuan Hung commune connecting with road from Tho Xuan town to Lam Son – Sao Vang urban area, Tho Xuan district

In August 2022, INVESTCORP Land Thanh Hoa Company Limited continued to implement items related to K98 road surface. The volume of work done in the month includes completion of K98 road surface compaction 1st layer, 50% of K98 soil work, 40% of rock embankment work, transportation of 40% of weathered soil to the collection ground. At the same time, INVESTCORP Land Thanh Hoa focused on constructing the drainage system, casting components and completing 90% of the work volume.

As planned in September 2022, INVESTCORP Land Thanh Hoa Company Limited will focus on executing the construction work items related to the roadbed and installing and completing the drainage system.