Construction progress update in July 2022 – Road project from Xuan Hung commune connecting with road from Tho Xuan town to Lam Son – Sao Vang urban area, Tho Xuan district

At the end of July 2022, INVESTCORP Land Thanh Hoa Co., Ltd. has focused on implementing and constructing items related to K98 road surface. The volume of work achieved in the month including earthwork construction reached 18%; transporting and shoveling weathered soil from the construction site to the specified place reached 30%. In addition, INVESTCORP Land Thanh Hoa has completed the casting of components and achieved 80% of the construction volume of the drainage system.

In August 2022, INVESTCORP Land Thanh Hoa will focus on implementation of K98 road embankment construction, installation and completion of drainage system, transportation of organic soil to the dump site.