Construction progress update in June 2022 – Typical Residential Area Infrastructure Project in Hoang Hoc Village, Dong Hoang Commune, Dong Son District, Thanh Hoa Province

At the end of June 2022, INVESTCORP Land Thanh Hoa Co., Ltd. has constructed the project and achieved 80% of the contract volume. The volume of work achieved in the month includes construction of the crushed stone subgrade type II reached 90%, the upper layer type I reached 70%, installation of curbs reached 95%, the pavement tiling reached 75%, planting trees reached 40% and water supply system reached 90%.

In July 2022, INVESTCORP Land Thanh Hoa continues to install water supply and drainage systems, construct crushed base and distribute asphalt on some of the main roads of the Project.