In October, 2022, INVESTCORP Land Thanh Hoa has carried out the construction of crushed stone for the subgrade II layer, reached 80% of the volume, construction and installation of curbs reached 98% and pavement paving reached 81%. At the same time, INVESTCORP Land Thanh Hoa has implemented to plant 98% of the tree volume.

Besides, INVESTCORP Land Thanh Hoa has also completed the construction of sewerage installations and substation installations. The total construction volume reached about 88% of the contract volume.

It is expected in November 2022, INVESTCORP Land Thanh Hoa will speed up to complete the construction of the crushed aggregate base course and carry out asphalt work for the remaining roads; complete the construction and installation of curbs, paving bricks, and the installation of water and electricity supply systems.