Construction progress updated in February 2023 – Key Technology Hanoi Factory Project Phase 2

By the end of February 2023, INVESTCORP 9 has completed the construction of reinforced concrete structures including foundations, foundation beams and columns of the factory and water tank.

In addition, ancillary items such as paint house, parking house, and garbage houses are also being implemented by INVESTCORP 9 in parallel.
It is expected that in March 2023, INVESTCORP 9 will complete the works of auxiliary items such as parking house and garbage house. Besides, it will continue to install steels, pour floor concrete and plastering and tiling finishing works for the factory, paint houses and pump rooms.