Construction progress updated in April 2023 - Project of renovating and upgrading rescue road in Truong Xuan commune to left dike of Chu River, Tho Xuan district, Thanh Hoa province

In April 2023, INVESTCORP Land Thanh Hoa Company completed the construction of items, including drainage, installation of electrical equipment, and construction of macadam, and asphalt pavement. Total construction output is estimated at 50% of the project volume.

As planned in May 2023, the Company will focus on implementing the construction of asphalt paving for the entire project, completing basically the items in the contract.