Construction progress updated in December 2022 – Typical Residential Area Infrastructure Project in Hoang Hoc Village, Dong Hoang Commune, Dong Son District, Thanh Hoa Province
In December 2022, INVESTCORP Land Thanh Hoa has focused on executing the work items in the contract. The works performed during the month includes road works, curbs, sidewalks, tree plant and campus.
For the roads, INVESTCORP Land Thanh Hoa has constructed crushed stone grade II reached 100% of the volume and crushed stone grade I reached 100% of the volume.
For the curbs, sidewalks, and tree plant, INVESTCORP Land Thanh Hoa has completed 100% of the curbs and 93% of sidewalk paving. In addition, the earthworks for ground leveling in the campus have also been constructed by INVESTCORP Land Thanh Hoa with 94% of the volume.
As planned to implement in January 2023, INVESTCORP Land Thanh Hoa will carry out pouring asphalt on the remaining roads of the project and basically complete the items signed in the contract.
- Announcement of Holiday schedule for Apr 30 and May 1, 2024
- Autoliv’s Chairman visits and works at the Autoliv Vietnam Factory project – Amata Song Khoai Industrial Park – Quang Yen Town – Quang Ninh Province
- Discussion program to celebrate the 114th anniversary of International Women′s Day March 8
- Groundbreaking ceremony of Jehong Textile Factory Project
- Enjoy spring of the new year Giap Thin 2024
- INVESTCORP Group begins the Spring of the Dragon year 2024
- INVESTCORP Group organizes the Year-End Party 2023 – Happy New Year 2024
- Announcement of Tet Holiday 2024