Construction progress updated in February 2023 - Project of renovating and upgrading rescue road in Truong Xuan commune to left dike of Chu river, Tho Xuan district, Thanh Hoa province

In February 2023, INVESTCORP Land Thanh Hoa continues to implement the construction of items and workloads according to the contract. The works performed during the month include drainage and lighting items.

For the drainage, the earthworks, the construction of crushed stone, and construction of concrete formwork and K98 compaction were completed by INVESTCORP Land Thanh Hoa about 78% of the volume. In addition, the excavation of cable trenches and electricity poles of the electricity and lighting was also 100% completed by INVESTCORP Land Thanh Hoa.

As planned, in March 2023, INVESTCORP Land Thanh Hoa will focus on completing the construction of drainage, structural concrete casting and construction of water-bound macadam to ensure quality and progress in the contract.