In February 2023, for the main factory package, the remaining works such as tiling, mechanics and foundations for machines of all kinds have been completed by INVESTCORP 15. For the exterior package, INVESTCORP 15 has also completed the handover of ancillary items, is implementing internal roads and installing sidewalk curbs.
It is expected that in March 2023, for the main factory package, INVESTCORP 15 will carry out spreading asphalt for internal roads and planting grass. In parallels, both the main factory package and the exterior one will be implemented by INVESTCORP 15 to fix defects and clean up for acceptance and handover.
Other news
- Announcement of Holiday schedule for Apr 30 and May 1, 2024
- Autoliv’s Chairman visits and works at the Autoliv Vietnam Factory project – Amata Song Khoai Industrial Park – Quang Yen Town – Quang Ninh Province
- Discussion program to celebrate the 114th anniversary of International Women′s Day March 8
- Groundbreaking ceremony of Jehong Textile Factory Project
- Enjoy spring of the new year Giap Thin 2024
- INVESTCORP Group begins the Spring of the Dragon year 2024
- INVESTCORP Group organizes the Year-End Party 2023 – Happy New Year 2024
- Announcement of Tet Holiday 2024
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED