Construction progress updated in February 2023 – Sao Mai Resort Project, Tho Lam Commune – Tho Xuan District – Thanh Hoa Province
In February 2023, INVESTCORP 6 continues to construct and complete items such as reception area, Rubby Four Seasons villa area, Bungalow under the lake and other ancillary items.
For the reception area, INVESTCORP 6 has completed the construction of the floor beams, the pier, the circular toilet and the excavation of the foundation, the construction of the floor of the stage area. The Rubby Four Seasons Villa and Bungalow under the lake have been continued to complete the tile roof, tiling, floor and interior by INVESTCORP 6.
In addition, in February 2023, INVESTCORP 6 has also completed the construction of generator rooms No.1 and 2, completed the structure of the frame and roof of the Tennis court and the laundry, and completed pouring pavement concrete for the roundabout. It is expected that in March 2023, INVESTCORP 6 will complete the frame and roof of the categories, and at the same time continue to implement other works according to the contract plan.
- Announcement of Holiday schedule for Apr 30 and May 1, 2024
- Autoliv’s Chairman visits and works at the Autoliv Vietnam Factory project – Amata Song Khoai Industrial Park – Quang Yen Town – Quang Ninh Province
- Discussion program to celebrate the 114th anniversary of International Women′s Day March 8
- Groundbreaking ceremony of Jehong Textile Factory Project
- Enjoy spring of the new year Giap Thin 2024
- INVESTCORP Group begins the Spring of the Dragon year 2024
- INVESTCORP Group organizes the Year-End Party 2023 – Happy New Year 2024
- Announcement of Tet Holiday 2024