Construction progress updated in January 2023 – Road project from Xuan Hung commune connecting with road from Tho Xuan town to Lam Son – Sao Vang urban area, Tho Xuan district

In January 2023, INVESTCORP Land Thanh Hoa continues to carry out the construction of traffic works. The works performed in the month including construction of water macadam for under layer of road surface reached 95%, construction of macadam for upper layer reached 95%, and construction of asphalt layer reached 82%. In addition, the construction of planting trees has also been completed 100% of the volume by INVESTCORP Land Thanh Hoa. Total construction output is estimated at 66%.

It is expected that at the end of February 2023, INVESTCORP Land Thanh Hoa will basically complete the items in the contract, including works related to the road foundation, completion of the water macadam and asphalt, implementation of pouring asphalt concrete and completing the installation of the drainage system.