Construction progress updated in January 2023 – Typical Residential Area Infrastructure Project in Hoang Hoc Village, Dong Hoang Commune, Dong Son District, Thanh Hoa Province

By the end of January 2023, INVESTCORP Land Thanh Hoa has basically completed the construction of drainage ditches and campus items together with the construction of watering asphalt to the road surface reaches 60% of the volume. Total construction volume is estimated at 97% of contract volume.

It is planned that in February 2023, INVESTCORP Land Thanh Hoa will carry out pouring asphalt on the remaining roads of the project, completing the construction of pavement tiles, completing the installation of the water and power supply system, and construction of green campus.