Construction progress updated in July 2017 at Taiyo Nippon Sanso Myanmar project.

By the end of July 2017, after executing the construction with the best efforts of the construction contractor –INVESCORP for nearly 05 months to catch up the tight schedule of the project, some main items have been finished. At present, all beam and slab formworks of the 1st floor and roof floor at the office building have been dismantled. Brickwork and plastering at the 1st floor have also been being executed and expected to finish in August 2017. Gypsum wall and ceiling are carried out in line.

At the gas pumping and ASP buildings, main items have also been finished. Rectification and painting works are implemented at some areas. Other remaining works will be executed and finished in August 2017 as proposed schedule.

At auxiliary areas such as power room, septic tank, warehouse, etc., some small resting works are urgently constructed such as painting finish, rectification and steel net.

In addition, concrete for internal road is being executed. For the external drainage, 90% of the workload has been finished and the whole item will be completed in August 2017.

Other news