Construction progress updated in July 2017 at Taiyo Nippon Sanso Myanmar project.
By the end of July 2017, after executing the construction with the best efforts of the construction contractor –INVESCORP for nearly 05 months to catch up the tight schedule of the project, some main items have been finished. At present, all beam and slab formworks of the 1st floor and roof floor at the office building have been dismantled. Brickwork and plastering at the 1st floor have also been being executed and expected to finish in August 2017. Gypsum wall and ceiling are carried out in line.
At the gas pumping and ASP buildings, main items have also been finished. Rectification and painting works are implemented at some areas. Other remaining works will be executed and finished in August 2017 as proposed schedule.
At auxiliary areas such as power room, septic tank, warehouse, etc., some small resting works are urgently constructed such as painting finish, rectification and steel net.
In addition, concrete for internal road is being executed. For the external drainage, 90% of the workload has been finished and the whole item will be completed in August 2017.
- Autoliv’s Chairman visits and works at the Autoliv Vietnam Factory project – Amata Song Khoai Industrial Park – Quang Yen Town – Quang Ninh Province
- Announcement of Holiday schedule for Apr 30 and May 1, 2024
- Discussion program to celebrate the 114th anniversary of International Women′s Day March 8
- Groundbreaking ceremony of Jehong Textile Factory Project
- Enjoy spring of the new year Giap Thin 2024
- INVESTCORP Group begins the Spring of the Dragon year 2024
- INVESTCORP Group organizes the Year-End Party 2023 – Happy New Year 2024
- Announcement of Tet Holiday 2024