Construction progress updated in July 2017– Biel Crystal Vietnam Factory Project.
More than two months after the groundbreaking ceremony on May 23, 2017, construction of the Biel Crystal Vietnam Factory project has been gradually come into stability. All of the temporary works for construction of the project such as fence, office, workers’ house, entrance gate and site signals have been finished.
At the Workshop area, after finishing piles, foundation and bracing beam; ground levelling, ground compaction and ground vibration were also executed and completed. As expectation, macadam laying and macadam compaction will be finished on Aug 05, 2018. After that, concrete for floor will be cast from Aug 10 to Aug 26, 2017. Brickwork and plastering for walls of the Workshop will be done next Aug 30, 2017.
In addition, steel structure for the workshop from axis X1 to axis X11 has been fabricated and will be installed from Aug 05 to Aug 12, 2017. It is expected that fabrication of the steel structure from axis X12 to axis X24 will have been done by Aug 13, 2017 and will be installed from Aug 12 to Aug 25, 2017.
At the office area, all of the concrete columns will be done on Aug 02, 2017, beam and slab concrete of the 2nd floor will be finished on Aug 15, 2017 and concrete of columns and roof beams at the 2nd floor will be finished on Aug 30, 2017.
- Autoliv’s Chairman visits and works at the Autoliv Vietnam Factory project – Amata Song Khoai Industrial Park – Quang Yen Town – Quang Ninh Province
- Announcement of Holiday schedule for Apr 30 and May 1, 2024
- Discussion program to celebrate the 114th anniversary of International Women′s Day March 8
- Groundbreaking ceremony of Jehong Textile Factory Project
- Enjoy spring of the new year Giap Thin 2024
- INVESTCORP Group begins the Spring of the Dragon year 2024
- INVESTCORP Group organizes the Year-End Party 2023 – Happy New Year 2024
- Announcement of Tet Holiday 2024