Construction progress updated in July 2022 – Expansion project of Meiko Quang Minh manufacturing and assembling electronic components factory - Phase 1

At the end of July 2022, the items of PCB building have been completed by INVESTCORP Dong Minh including construction of reinforcement, formworks, and concrete pouring after more than two months of commencement of the Expansion project of Meiko Quang Minh manufacturing and assembling electronic components factory - Phase 1 of Meiko Electronics Quang Minh Co., Ltd. Other finishing works are under construction such as leveling, compaction, 1st floor columns and 2nd floor beams.

The underground water tank has been completed walls, columns and waterproofing work. Currently, INVESTCORP Dong Minh is installing the cover of the underground water tank and filling sand for the tank walls.

Ancillary items such as electric house, cooling house & compressed air machine, and boiler house are completed 100% of foundation work and construction of 1st floor columns.

In August 2022, INVESTCORP Dong Minh will continue to carry out the construction of foundation pit filling and compaction, sand filling of tank walls.

 

 