Construction progress updated in July 2022 – Project of Repairing damage to foundation, road surface, drainage system and traffic safety at section Km51+600 - Km53+500; Km57+00 - Km59+700, National way 47, Thanh Hoa province

In July 2022, INVESTCORP Land Thanh Hoa Co., Ltd. has mobilized human resources and equipment to implement the items such as digging molds, backfilling and expanding the roadside reached 50%, construction of asphalt screeding and emulsion irrigation reached 50%, casting components reached 90% of the volume.

As planned in August 2022, INVESTCORP Land Thanh Hoa will continue to carry out construction works related to expanding and reinforcing road pavements and installing concrete slabs.