Construction progress updated in July 2023 - Project of renovating and upgrading rescue road in Truong Xuan commune to left dike of Chu River, Tho Xuan district, Thanh Hoa province

In July 2023, INVESTCORP Land Thanh Hoa basically completed the drainage system, installed the lighting system, and completed the construction of crushed stone and spread asphalt for the road surface. Total construction output is estimated at 50% of the contract volume.

As planned in August 2023, INVESTCORP Land Thanh Hoa will focus on implementing the construction of asphalt spreading for the entire project, basically completing the items in the contract to conduct inspection and handover to the Investor to put into use.