Construction progress updated in June 2022 – Project of Repairing damage to foundation, road surface, drainage system and traffic safety at section Km51+600 - Km53+500; Km57+00 - Km59+700, National way 47, Thanh Hoa province

In June 2022, INVESTCORP Land Thanh Hoa Co., Ltd. has mobilized human resources and equipment to carry out the construction of items including: digging roadbed, compacting and reinforcing to expand curbs, casting components. Besides, the repair work of the drainage system has reached 35% of the volume.

As planned in July 2022, INVESTCORP Land Thanh Hoa continues to carry out the construction of damaged road surface treatment works and drainage system.