Construction progress updated in March 2023 – Key Technology Hanoi Factory Project Phase 2

By the end of March 2023, INVESTCORP 9 has completed 60% of the project's workload, including backfilling and lining for the factory floor reached 60%, plastering the factory wall reached 90%; completed 100% of the foundation base and house column painting; completed concrete pouring of the foundation floor and erected steel columns for the garbage house; completed steel erection and roof beam formwork.

According to the plan in April 2023, INVESTCORP 9 will mainly focus on pouring concrete for the factory floor and pumping house and implementing finishing works for toilets. It is expected that by the end of April 2023, INVESTCORP 9 will complete 90% of the project workload.