Construction progress updated in March 2023 – Key Technology Hanoi Factory Project Phase 2
By the end of March 2023, INVESTCORP 9 has completed 60% of the project's workload, including backfilling and lining for the factory floor reached 60%, plastering the factory wall reached 90%; completed 100% of the foundation base and house column painting; completed concrete pouring of the foundation floor and erected steel columns for the garbage house; completed steel erection and roof beam formwork.
According to the plan in April 2023, INVESTCORP 9 will mainly focus on pouring concrete for the factory floor and pumping house and implementing finishing works for toilets. It is expected that by the end of April 2023, INVESTCORP 9 will complete 90% of the project workload.
Other news
- Announcement of Holiday schedule for Apr 30 and May 1, 2024
- Autoliv’s Chairman visits and works at the Autoliv Vietnam Factory project – Amata Song Khoai Industrial Park – Quang Yen Town – Quang Ninh Province
- Discussion program to celebrate the 114th anniversary of International Women′s Day March 8
- Groundbreaking ceremony of Jehong Textile Factory Project
- Enjoy spring of the new year Giap Thin 2024
- INVESTCORP Group begins the Spring of the Dragon year 2024
- INVESTCORP Group organizes the Year-End Party 2023 – Happy New Year 2024
- Announcement of Tet Holiday 2024
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED