Construction progress updated in March 2023 - Project of renovating and upgrading rescue road in Truong Xuan commune to left dike of Chu river, Tho Xuan district, Thanh Hoa province

In March 2023, the construction of soil excavation, crushed stone, concrete formwork, K98 compaction, and concrete pouring to return the drainage ditch were 100% completed by INVESTCORP Land Thanh Hoa. At the same time, the work of digging and spreading underground cables to install electrical equipment, the construction of macadam and road asphalt have also been completed. Total construction output is estimated at 49% of the contract volume.

According to plan in April 2023, INVESTCORP Land Thanh Hoa will focus on implementing the construction of asphalt spreading for all roads under the project.