Construction progress updated in March 2023 - Renovation and upgrading project of provincial road 506B, section from Tho Lap commune to Xuan Tin commune, Tho Xuan district

At the beginning of March 2023, INVESTCORP Land Thanh Hoa gathered machinery and human resources to carry out the construction of work items according to the signed contract.

In March 2023, the Company mainly focused on road surface items, excavation and transportation of weathered soil reached 20% of the volume; transportation and embankment of K95 reached 12% of the volume.

According to the April 2023 plan, INVESTCORP Land Thanh Hoa will continue to execute the construction of road surface items, speed up the excavation of weathered soil and embankment of K95 to ensure the quality and progress in the contract.