Construction progress updated in March 2023 - Vina Ito Factory Project Phase 2

In March 2023, INVESTCORP 15 completed pouring concrete of the factory floor; along with that, tiling the toilet area of the factory, installing curbs, completing manholes, and completing garbage houses were also completed.

As planned in April 2023, INVESTCORP 15 will carry out asphalting internal roads, and at the same time urgently execute cleaning work and defect repair to implement internal acceptance with the Main contractor before handing over to the Investor to put into operation and use.