Construction progress updated in May 2023 – Key Technology Hanoi Factory Project Phase 2

By the end of May 2023, INVESTCORP 9 has completed 85% of the work volume of the whole project, including plastering the main factory at 98%, erecting steel and concreting the main factory floor at 90%; erecting steel and pouring concrete of painting house reached 50%.

At the same time, the auxiliary items have been completed by INVESTCORP 9, including the motorbike parking house, the car parking house, the water tank, and the pump house.

As planned in June 2023, INVESTCORP 9 will complete 100% of the whole project, conduct an acceptance test, repair minor errors together with the Main Contractor, and prepare for acceptance and handover to the Investor.


 