Sao Mai New Urban Area Project is invested by Sao Mai Group and the main contractor Vistar Joint Stock Company with a construction area of 704,354 m2. INVESTCORP Group has signed a contract to execute the project's pavement paving package and INVESTCORP 6 will directly execute the package.

The package was started on October 15, 2022 and is expected to finish on January 30, 2023. In October 2022, INVESTCORP 6 has started to implement pavement laying, concrete pouring and pavement paving in all areas. As planned in November 2022, INVESTCORP 6 will continue the paving work in the areas where the Investor has handed over the site.