Construction progress updated in September 2022 – Project of Repairing damage to foundation, road surface, drainage system and traffic safety at section Km51+600 - Km53+500; Km57+00 - Km59+700, National way 47, Thanh Hoa province
In September 2022, INVESTCORP Land Thanh Hoa Company Limited has focused on speeding up the contract progress. Items are under construction such as drainage, repair of rubber road surface and sagging.
For the drainage item, in September, INVESTCORP Land Thanh Hoa has implemented 50% of the excavation and installation of trench components; Excavation of old structural road surface, construction of crushed stone surface and asphalt spreading has been completed. Total completed volume is estimated at 26%.
As planned in October 2022, INVESTCORP Land Thanh Hoa continues to accelerate the construction progress to complete the works related to the road surface, drainage system and carry out the construction of asphalt concrete.
Other news
- Autoliv’s Chairman visits and works at the Autoliv Vietnam Factory project – Amata Song Khoai Industrial Park – Quang Yen Town – Quang Ninh Province
- Announcement of Holiday schedule for Apr 30 and May 1, 2024
- Discussion program to celebrate the 114th anniversary of International Women′s Day March 8
- Groundbreaking ceremony of Jehong Textile Factory Project
- Enjoy spring of the new year Giap Thin 2024
- INVESTCORP Group begins the Spring of the Dragon year 2024
- INVESTCORP Group organizes the Year-End Party 2023 – Happy New Year 2024
- Announcement of Tet Holiday 2024
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED