Update constructing progress in June 2017 – Vientiane (Laos) international airport terminal expansion construction project
As of the end of June 2017, at the Western passenger terminal, all of the interior and exterior completion works have been synchronously implemented in order to ensure partial handover to the Owner to put into use at the end of August 2017. In addition, other works have been done at the same time.
At the Eastern passenger terminal, construction of floor beam structure have been being set up quickly to speed up the schedule. It is estimated that the whole main structure of the Eastern passenger terminal will be completed in July 2017.
In addition, at the International concourse, the ceiling and partition items have been started. As the schedule signed in the agreement, in December 2017, INVESTCORP will hand-over the Eastern passenger terminal and International concourse to the Investor for putting into operation.
- Autoliv’s Chairman visits and works at the Autoliv Vietnam Factory project – Amata Song Khoai Industrial Park – Quang Yen Town – Quang Ninh Province
- Announcement of Holiday schedule for Apr 30 and May 1, 2024
- Discussion program to celebrate the 114th anniversary of International Women′s Day March 8
- Groundbreaking ceremony of Jehong Textile Factory Project
- Enjoy spring of the new year Giap Thin 2024
- INVESTCORP Group begins the Spring of the Dragon year 2024
- INVESTCORP Group organizes the Year-End Party 2023 – Happy New Year 2024
- Announcement of Tet Holiday 2024