Update constructing progress in June 2017 – Vientiane (Laos) international airport terminal expansion construction project

As of the end of June 2017, at the Western passenger terminal, all of the interior and exterior completion works have been synchronously implemented in order to ensure partial handover to the Owner to put into use at the end of August 2017. In addition, other works have been done at the same time.

At the Eastern passenger terminal, construction of floor beam structure have been being set up quickly to speed up the schedule. It is estimated that the whole main structure of the Eastern passenger terminal will be completed in July 2017.

In addition, at the International concourse, the ceiling and partition items have been started. As the schedule signed in the agreement, in December 2017, INVESTCORP will hand-over the Eastern passenger terminal and International concourse to the Investor for putting into operation.