Update construction progress – Crystal Martin Vietnam factory project in December 2020

At the end of December 2020, all ceilings, drywall, aluminum and glass walls, mobile walls, paintwork, wooden doors and interior cabinets at the Renovation of the 6th floor of R1C building into an office - Crystal Martin Vietnam Factory project have been completed by INVESTCORP. The Vinyl flooring work has been completed 80% of the workload. It is expected that the polycarbonate wall will be completed on January 10, 2021. Other finishing works such as repairing, retouching and cleaning are also under construction.

It is expected that the entire project will be completed before January 20, 2021 and will be inspected and handed over to the Investor.