Update construction progress – Crystal Martin Vietnam factory project in November 2020
At the end of November 2020, INVESTCORP has completed all toilet tiling, 95% of the gypsum ceilings and partitions and 60% of wooden doors and aluminum - glass walls at the renovation of the 6th floor of R1C building into an office - Crystal Martin Vietnam factory project. Currently, INVESTCORP is under construction of interior items including cabinets, mobile walls, Polycarbonate walls and surface finishing for Vinyl flooring. The mockup room has been completed and approved by the Investor.
It is expected that in December 2020, all finishing items such as wooden doors, aluminum and glass, toilet walls, mobile walls, interior cabinets and Vinyl flooring will be completed to prepare for inspection and handover to the Investor.
Other news
- Announcement of Holiday schedule for Apr 30 and May 1, 2024
- Autoliv’s Chairman visits and works at the Autoliv Vietnam Factory project – Amata Song Khoai Industrial Park – Quang Yen Town – Quang Ninh Province
- Discussion program to celebrate the 114th anniversary of International Women′s Day March 8
- Groundbreaking ceremony of Jehong Textile Factory Project
- Enjoy spring of the new year Giap Thin 2024
- INVESTCORP Group begins the Spring of the Dragon year 2024
- INVESTCORP Group organizes the Year-End Party 2023 – Happy New Year 2024
- Announcement of Tet Holiday 2024
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED