Update construction progress – Crystal Martin Vietnam factory project in October 2020
In October 2020, the renovation of the 6th floor of R1C building into an office - Crystal Martin Vietnam factory project continued to be constructed by INVESTCORP according to schedule.
At present, INVESTCORP has completed the painting of ceiling beam, installation of outdoor windows and toilet wall cladding. The mockup room has also been constructed. The waterproofing and toilet floor works are being executed in parallel with the ceiling, gypsum partitions and aluminum and glass walls. Wood doors, interior cabinets, mobile partitions, polycarbonate partitions are in the process at the factory.
According to the plan in November 2020, INVESTCORP will carry out the erection of all wooden doors, glass walls, mobile partitions, Vinyl ground and interior cabinets.
- Autoliv’s Chairman visits and works at the Autoliv Vietnam Factory project – Amata Song Khoai Industrial Park – Quang Yen Town – Quang Ninh Province
- Announcement of Holiday schedule for Apr 30 and May 1, 2024
- Discussion program to celebrate the 114th anniversary of International Women′s Day March 8
- Groundbreaking ceremony of Jehong Textile Factory Project
- Enjoy spring of the new year Giap Thin 2024
- INVESTCORP Group begins the Spring of the Dragon year 2024
- INVESTCORP Group organizes the Year-End Party 2023 – Happy New Year 2024
- Announcement of Tet Holiday 2024