Update construction progress – Crystal Martin Vietnam factory project in October 2020

In October 2020, the renovation of the 6th floor of R1C building into an office - Crystal Martin Vietnam factory project continued to be constructed by INVESTCORP according to schedule.

At present, INVESTCORP has completed the painting of ceiling beam, installation of outdoor windows and toilet wall cladding. The mockup room has also been constructed. The waterproofing and toilet floor works are being executed in parallel with the ceiling, gypsum partitions and aluminum and glass walls. Wood doors, interior cabinets, mobile partitions, polycarbonate partitions are in the process at the factory.

According to the plan in November 2020, INVESTCORP will carry out the erection of all wooden doors, glass walls, mobile partitions, Vinyl ground and interior cabinets.