Update construction progress – Crystal Martin Vietnam factory project in September 2020

In September 2020, INVESTCORP continued to execute the renovation of the 6th floor of R1C building into an office at the Crystal Martin Vietnam factory project.

At present, INVESTCORP has completed the compensation of foundation concrete, completed demolishing and opening external windows. The internal plastering works, toilet tiling, the construction of mockup room, the painting and skimcoat of ceiling beams and gypsum walls are under construction.

It is expected that in October 2020, INVESTCORP will basically complete the toilet tiling, painting and skimcoat of ceiling beams and gypsum walls, erection of aluminum doors and wooden doors. Some items such as vinyl ground, interior cabinets will be executed in late October 2020.