Update construction progress in April 2017 – Taiyo Nippon Sanso Myanmar Project.

Up to the end of April 2017, after nearly two months of construction with earnest and urgency, Taiyo Nippon Sanso project is always follow-up and ensures the progress requirements of the Investor.

At the main buildings such as office building, gas pump station, AFP building, construction of base structure has been basically completed. Currently, at the office, all scaffolding and formwork have been erected for construction of the floor beams of the second floor.

At the auxiliary works such as power room, septic tank, warehouse … construction still continues to be accelerated paralleling with progress of the main building. At the end of April 2017, the roof beams and slabs of the electrical room have been completed and foundation work, spandrel beams, etc … of the warehouse have been completed.

In addition, outdoor work items such as internal road, rainwater drainage system, etc. … have been completed 70% of the workload.

By the end of Apr 2017, the total workload of the Taiyo Nippon Sanso project has gained 40% of scope of works.