Update construction progress in April 2017 – Taiyo Nippon Sanso Myanmar Project.
Up to the end of April 2017, after nearly two months of construction with earnest and urgency, Taiyo Nippon Sanso project is always follow-up and ensures the progress requirements of the Investor.
At the main buildings such as office building, gas pump station, AFP building, construction of base structure has been basically completed. Currently, at the office, all scaffolding and formwork have been erected for construction of the floor beams of the second floor.
At the auxiliary works such as power room, septic tank, warehouse … construction still continues to be accelerated paralleling with progress of the main building. At the end of April 2017, the roof beams and slabs of the electrical room have been completed and foundation work, spandrel beams, etc … of the warehouse have been completed.
In addition, outdoor work items such as internal road, rainwater drainage system, etc. … have been completed 70% of the workload.
By the end of Apr 2017, the total workload of the Taiyo Nippon Sanso project has gained 40% of scope of works.
- Autoliv’s Chairman visits and works at the Autoliv Vietnam Factory project – Amata Song Khoai Industrial Park – Quang Yen Town – Quang Ninh Province
- Announcement of Holiday schedule for Apr 30 and May 1, 2024
- Discussion program to celebrate the 114th anniversary of International Women′s Day March 8
- Groundbreaking ceremony of Jehong Textile Factory Project
- Enjoy spring of the new year Giap Thin 2024
- INVESTCORP Group begins the Spring of the Dragon year 2024
- INVESTCORP Group organizes the Year-End Party 2023 – Happy New Year 2024
- Announcement of Tet Holiday 2024