Update construction progress in April 2017 – Vientiane (Laos) international airport terminal expansion project
At the end of April 2017, at Vientiane (Laos) international airport terminal expansion project, construction of the structure is being accelerated to complete the final stages.
At the Western passenger terminal, the whole structure has been completed. Finishing works such as plastering and internal and external tiling of the building are actively hastened. In addition, outdoor work items such as excavation for the drainage systems have been implemented and are expected to be completed in May 2017.
At the Eastern passenger terminal, construction of columns of the first floor has been completed. Currently, the formwork and scaffolding have been erected to prepare for casting concrete of the floor beams of the 2nd floor in May 2017.
In addition, at the International concourse, all of steel structure work has been completed, ceiling and partition works have been implemented since mid-month and is being accelerated actively. As of the end of April 2017, total construction work quantity of ceiling and wall construction achieved 50% of total workload.
- Autoliv’s Chairman visits and works at the Autoliv Vietnam Factory project – Amata Song Khoai Industrial Park – Quang Yen Town – Quang Ninh Province
- Announcement of Holiday schedule for Apr 30 and May 1, 2024
- Discussion program to celebrate the 114th anniversary of International Women′s Day March 8
- Groundbreaking ceremony of Jehong Textile Factory Project
- Enjoy spring of the new year Giap Thin 2024
- INVESTCORP Group begins the Spring of the Dragon year 2024
- INVESTCORP Group organizes the Year-End Party 2023 – Happy New Year 2024
- Announcement of Tet Holiday 2024