Update construction progress in Aug 2017 at Taiyo Nippon Sanso Myanmar Project.

In August 2017, with construction efforts of the Contractor INVESTCORP to ensure progress of the project, at the Office building, INVESTCORP has completed the ground work and is carrying out the gypsum ceiling-partition and painting work. All of the key items will be completed in September 2017.

At the auxiliary areas, the main items are also being completed and repaired for timely handing-over to the Owner in September as expected schedule.

Concrete work for the internal road has been completed 70% of the total workload. The entire concrete work of the road will be finished in September 2017.

For the outdoor rainwater drainage system, INVESTCORP has completed 95% of the total workload.