Update construction progress in December 2020 – Dong Nam Residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province

In December 2020, INVESTCORP Land Thanh Hoa continued to focus on the construction of road’s surface structures such as the treatment of weak roadbeds due to being flooded during storms, the excavation of organic soil of roads No. 4, 5, 10, 11 and 13. The K95 and K98 backfilling work for the roads has reached 90% of the workload.

It is expected that in January 2021, INVESTCORP Land Thanh Hoa will complete the entire K95, K98 soil layers and cast structures related to drainage system. The installation of pipes for surface sewage, wastewater drainage and base construction will reach 30% of the total workload according to the contract.