Update construction progress in May 2017 – Taiyo Nippon Sanso Myanmar Project.
In May 2017, it was rainy in Yangon, the works at the Taiyo Nippon Sanso project have been encountered many difficulties. However, with the determined spirit, the team of engineers and workers on the construction site has worked hard to ensure the expected schedule.
At the office area, formwork and rebar of slabs & beams on the 2nd floor have been accelerated to ensure the concrete pouring plan which is scheduled to start in early June 2017. The utility facilities such as the electric chambers, septic tanks, warehouses, etc. are being proceeding walls and foundations.
External work such as the drainage ditch system has reached 80% of total workload. In addition, the road work has completed the base & sub-base for embankment.
Other news
- Congratulations to VDL ETG Group (Netherlands) on inauguration of its first factory in Vietnam
- INVESTCORP Group welcomes and works with the delegation from the German Chamber of Commerce and Industry (IHK) Region Stuttgart
- Groundbreaking Ceremony of staBOO Thanh Hoa OSB Bamboo Board Manufacturing Plant
- Announcement of Holiday schedule for Apr 30 and May 1, 2025
- Seminar to celebrate International Women′s Day March 8
- Spring travel of At Ty 2025
- INVESTCORP Group opens the spring of year At Ty 2025
- Year-end Ceremony 2024 - Welcoming the New Year 2025
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED