Update construction progress in November 2020 – Dong Nam Residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province

At the end of November 2020, Dong Nam residential infrastructure continued to be postponed due to rainy weather affecting the excavation and infrastructure construction. Currently, INVESTCORP Land Thanh Hoa has surveyed, made method statement and pumped water, executed drainage and treated the flooded area.

It is expected that in December 2020, INVESTCORP Land Thanh Hoa will continue to treat flooded roads, excavate and remove organic mud, embank the remaining roads and complete the K95 soil filling for all roads in the project.