Update construction progress in Sep 2017 at Taiyo Nippon Sanso Myanmar Project.

In September 2017, the Construction contractor INVESTCORP continued completing and handing-over some other items of the auxiliary areas at the Taiyo Nippon Sanso Myanmar project to the Owner such as ASP building, power room and substation.

At the office building, brickwork and plastering work have been completed and continue implementing gypsum ceiling and partition, painting and tiling works. As expected, by October 15, 2017, all the above works will have also been completed.

Other items such as rubber floor of the gas pumping building and floor of the warehouse are also being carried out and finished.

For the external road category, 80% of the workload has been implemented and it is expected by October 5, 2017, concrete of the road will be done.