Update construction progress – Lakeside Service Apartment (Myanmar) project in July 2020
INVESTCORP Myanmar is now executing piling work for the basement construction of the Lakeside service apartment (Myanmar) project.
It is expected that in August 2020, INVESTCORP Myanmar will complete the piling and start moving to excavation work. The shoring system has been fabricated and is being gradually delivered to the site. Preparations for structural construction and finishing work are being carried out according to the overall progress of the project.
Other news
- Announcement of Holiday schedule for Apr 30 and May 1, 2024
- Autoliv’s Chairman visits and works at the Autoliv Vietnam Factory project – Amata Song Khoai Industrial Park – Quang Yen Town – Quang Ninh Province
- Discussion program to celebrate the 114th anniversary of International Women′s Day March 8
- Groundbreaking ceremony of Jehong Textile Factory Project
- Enjoy spring of the new year Giap Thin 2024
- INVESTCORP Group begins the Spring of the Dragon year 2024
- INVESTCORP Group organizes the Year-End Party 2023 – Happy New Year 2024
- Announcement of Tet Holiday 2024
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED