Update construction progress – Lakeside Service Apartment (Myanmar) project in June 2021
At the end of June 2021, INVESTCORP Myanmar has completed dismantling the pile support system, completed 100% of the reinforced concrete volume of the basement walls and 30% of the reinforced concrete structure of the floor beams. Currently, the pile extraction, waterproofing and sanding of the basement walls are starting to be implemented.
It is expected that in July 2021, INVESTCORP Myanmar will focus on speeding up the construction progress of the basement reinforced concrete structures, completing pouring concrete of the first floor beams, waterproofing and sanding basement exterior and 80% of piling work. The dismantling of the first floor beam formwork will also be started at the end of July 2021.
Other news
- Autoliv’s Chairman visits and works at the Autoliv Vietnam Factory project – Amata Song Khoai Industrial Park – Quang Yen Town – Quang Ninh Province
- Announcement of Holiday schedule for Apr 30 and May 1, 2024
- Discussion program to celebrate the 114th anniversary of International Women′s Day March 8
- Groundbreaking ceremony of Jehong Textile Factory Project
- Enjoy spring of the new year Giap Thin 2024
- INVESTCORP Group begins the Spring of the Dragon year 2024
- INVESTCORP Group organizes the Year-End Party 2023 – Happy New Year 2024
- Announcement of Tet Holiday 2024
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED