Update construction progress – Lakeside Service Apartment (Myanmar) project in May 2021
After the temporary suspension of construction according to the direction of the Investor to ensure the safety of employees, the Lakeside Service Apartment (Myanmar) project has begun to construct again from April 27, 2021.
In May 2021, INVESTCORP Myanmar has completed the construction of 100% of the basement floor and 70% of the dismantling of pilling support system. Reinforced concrete structures for basement walls, waterproofing and sand filling have also been completed 60% of the work volume.
Construction plan expected in June 2021, INVESTCORP Myanmar will complete casting concrete of the basement wall structure, complete 100% of the dismantling of the pilling support system and 60% of the reinforced concrete of the 1st floor beams. In addition, waterproofing, sand filling outside the basement walls and surface finishing of the concrete structure will also be completed to implement the basement acceptance work. The sheet pile extraction will start from the end of June 2021.
- Autoliv’s Chairman visits and works at the Autoliv Vietnam Factory project – Amata Song Khoai Industrial Park – Quang Yen Town – Quang Ninh Province
- Announcement of Holiday schedule for Apr 30 and May 1, 2024
- Discussion program to celebrate the 114th anniversary of International Women′s Day March 8
- Groundbreaking ceremony of Jehong Textile Factory Project
- Enjoy spring of the new year Giap Thin 2024
- INVESTCORP Group begins the Spring of the Dragon year 2024
- INVESTCORP Group organizes the Year-End Party 2023 – Happy New Year 2024
- Announcement of Tet Holiday 2024