Update construction progress – Manufacturing eco-friendly decor product project in June 2021

At the end of June 2021, INVESTCORP 15 has completed the entire construction of mass piling work for the factory and office area of the Manufacturing eco-friendly decor product project; completed 95% of concrete foundation and bracing of the factory foundation, 30% of the cold tank concrete cover, concrete of the ditch’s bottom and walls. The excavation of the basement and the fire tank has also been completed.

It is expected that in July 2021, INVESTCORP 15 will complete the construction of the entire concrete foundation, ground, and walls of the office area and at the same time, build the factory walls and pour the wall concrete of the chemical warehouse.