Update construction progress – Meiko Quang Minh electronics assembling factory project in Mar 2020

In Mar 2020, INVESTCORP completed temporary items for construction of the Meiko Quang Minh electronics assembling factory project such as office, warehouse, workers’ dormitory, temporary road so on.

At the main factory, INVESTCORP has completed mass piles, foundation excavation and casting lean concrete; completed fabrication, erection of reinforcement and formwork of foundation brace. The formwork of the foundation frame and pedestal are also done. Construction of the base layer and compaction of the floor has reached 50% of the workload.

At the auxiliary items, all piling work of the chiller room, boiler room, and pump room have been completed.

The Meiko Quang Minh electronics assembling factory project was commenced in Nov 2019. As expectation, the project will have been completed and handed over to the Investor - Meiko electronics Quang Minh Company Ltd. in Sep 2020.