Update construction progress – Multifunctional house of Tho Xuan High school No 4, Tho Xuan district in April 2021

In April 2021, at the Multifunctional house project of Tho Xuan 4 High School, INVESTCORP Land Thanh Hoa continued to execute the superstructure of the Multifunctional house. The works completed in the month include: 95% of the internal and external plastering works; completing tiling toilets, painting the exterior walls of the house, constructing wastewater drainage ditches and three-step stairs.

It is expected that in May 2021, INVESTCORP Land Thanh Hoa will complete architectural items such as plastering and wall painting; construction and installation of roof steel structure and roofing; construction and installation of electrical systems, drainage systems, installation of electrical equipment, water equipment; construction of wooden floor, installation of door system... complete and hand over the whole project to the Investor.