Update construction progress – Multifunctional house of Tho Xuan High school No 4, Tho Xuan district in March 2021

At the end of March 2021, INVESTCORP Land Thanh Hoa completed 80% of the internal and external plastering work, completed ground concrete of the Multifunctional house project of Tho Xuan High school No. 4 and fabricated roof structural steel frame at the factory.

As planned in April 2021, INVESTCORP Land Thanh Hoa will complete architectural items such as plastering, wall painting, steel frame and corrugated roofing; construct and install electrical systems, drainage systems, electrical equipment and water equipment; carry out tiling work, install wooden floor, install steel core plastic door system as well as complete and hand over the project in early May 2021.