Update construction progress of HTMP mold and plastic part manufacturing project in Feb 2019
By the end of Feb 2019, after nearly 7 months of construction at the HTMP mold and plastic part manufacturing project, INVESTCORP has completed to 95% of the indoor items. At the moment, the final finishing works are carried out.
Outdoor items such as concrete road, drainage system, fence, gate and greenery work ect. will be completed by 15 Mar 2019.
The whole project will be inspected and handed over to the Owner to put into use on 20 Mar 2019.
Other news
- Autoliv’s Chairman visits and works at the Autoliv Vietnam Factory project – Amata Song Khoai Industrial Park – Quang Yen Town – Quang Ninh Province
- Announcement of Holiday schedule for Apr 30 and May 1, 2024
- Discussion program to celebrate the 114th anniversary of International Women′s Day March 8
- Groundbreaking ceremony of Jehong Textile Factory Project
- Enjoy spring of the new year Giap Thin 2024
- INVESTCORP Group begins the Spring of the Dragon year 2024
- INVESTCORP Group organizes the Year-End Party 2023 – Happy New Year 2024
- Announcement of Tet Holiday 2024
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED