Update construction progress of Myanmar Meranti project’s Ruby in Feb 2019
In Feb 2019, at the Myanmar Meranti project’s Ruby of Meranti Ltd., INVESTCORP Myanmar continues to implement brickwork and plastering work of some ancillary houses.
For the additional PIT in the workshop, at present, INVESTCORP Myanmar has finished casting 90% of concrete workload and continues to proceed reinforcement and formwork of the foundation base and wall. As expected, the whole PIT work will be completed in Mar 2019.
At the main workshop, floor concrete has been finished 70% of the workload and is being continued implementing the rest. Other finishing works will be carried out later.
Other news
- Autoliv’s Chairman visits and works at the Autoliv Vietnam Factory project – Amata Song Khoai Industrial Park – Quang Yen Town – Quang Ninh Province
- Announcement of Holiday schedule for Apr 30 and May 1, 2024
- Discussion program to celebrate the 114th anniversary of International Women′s Day March 8
- Groundbreaking ceremony of Jehong Textile Factory Project
- Enjoy spring of the new year Giap Thin 2024
- INVESTCORP Group begins the Spring of the Dragon year 2024
- INVESTCORP Group organizes the Year-End Party 2023 – Happy New Year 2024
- Announcement of Tet Holiday 2024
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED