Update construction progress of Myanmar Meranti project’s Ruby in Feb 2019

In Feb 2019, at the Myanmar Meranti project’s Ruby of Meranti Ltd., INVESTCORP Myanmar continues to implement brickwork and plastering work of some ancillary houses.

For the additional PIT in the workshop, at present, INVESTCORP Myanmar has finished casting 90% of concrete workload and continues to proceed reinforcement and formwork of the foundation base and wall. As expected, the whole PIT work will be completed in Mar 2019.

At the main workshop, floor concrete has been finished 70% of the workload and is being continued implementing the rest. Other finishing works will be carried out later.