Update construction progress of New warehouse project – Peony factory in January 2021
The new warehouse project - Peony factory was commenced on December 1, 2020 with an area of 1760 m2 in the form of steel-frame house, corrugated iron walls combined with 1m high walls and concrete ground.
At the end of January 2021, INVESTCORP completed plastering work, erection of steel frame structure, preparation of corrugated iron walls, roof and ground concrete.
Currently, the project is in the finishing process and it is expected that the main items will be basically completed before the Lunar New Year.


Other news
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
- INVESTCORP Group Organizes Annual Employee Health Check-up Program 2025
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED