Update construction progress of projects in August, 2016
Maple Garment Factory’s Project – Peony branch
Under strict supervision of the Board of Directors and with right spirit of all engineers and worker teams, the construction project of Maple Garment Factory – Peony branch has successfully maintained progress, quality and safety after constructing nearly 4 months.
By late August, 2016, steel structure was finished at factory areas, now switching to other tasks. Roof sheeting is carried out at Cutting workshop No.1 and Sewing workshop No.2. Meanwhile, wall building is brought into progress after completing steel structure and metal sheet roof at Sewing workshop No. 1.
In addition, auxiliary categories including Parking area, Canteen, water tank and waste water treatment tank, etc… continue to be speeded up to meet the Owner’s requirements.
- Autoliv’s Chairman visits and works at the Autoliv Vietnam Factory project – Amata Song Khoai Industrial Park – Quang Yen Town – Quang Ninh Province
- Announcement of Holiday schedule for Apr 30 and May 1, 2024
- Discussion program to celebrate the 114th anniversary of International Women′s Day March 8
- Groundbreaking ceremony of Jehong Textile Factory Project
- Enjoy spring of the new year Giap Thin 2024
- INVESTCORP Group begins the Spring of the Dragon year 2024
- INVESTCORP Group organizes the Year-End Party 2023 – Happy New Year 2024
- Announcement of Tet Holiday 2024