Update construction progress of Tamada Office and Warehouse project in August 2019
In August 2019, finishing work of the main factory of Tamada office and warehouse project was completed up to 95%.
In the office area, INVESTCORP Myanmar has completed tiling work, painting and installation of glass doors and windows at the 1st floor and is conducting construction of those works at the second floor. The internal painting work at the 2nd floor is also being completed and handed over by room.
Outdoor items such as plastering work and finish of fence have been executed up to 90%, the drainage system has been completed final works. Leveling of grass area around the house and painting of fence and gate are also carried out in parallel.
It is expected that the whole project will be completed and handed over by the end of September 2019.
- Announcement of Holiday schedule for Apr 30 and May 1, 2024
- Autoliv’s Chairman visits and works at the Autoliv Vietnam Factory project – Amata Song Khoai Industrial Park – Quang Yen Town – Quang Ninh Province
- Discussion program to celebrate the 114th anniversary of International Women′s Day March 8
- Groundbreaking ceremony of Jehong Textile Factory Project
- Enjoy spring of the new year Giap Thin 2024
- INVESTCORP Group begins the Spring of the Dragon year 2024
- INVESTCORP Group organizes the Year-End Party 2023 – Happy New Year 2024
- Announcement of Tet Holiday 2024